East Harbor Phase I Outfall Pipe Repair and Dune Restoration Project Schedule
Posted on: December 21, 2018 - 11:20am
The East Harbor Phase I Outfall Pipe Repair and Dune Restoration project is underway. Staging for construction will begin Friday December 21, 2018.
Staging will include the following:
- Closure of Noons' Landing parking lot from December 21, 2018 through mid-May 2019.
- Closure of Beach Point parking lot from December 21, 208 through mid-May 2019.
- Closure of Noons' Landing Beach access from December 21, 2018 through mid-May 2019. Beach Point beach access will remain open.
- Traffic control consisting of signage, barricades and temporary traffic lighting will be installed in the area of Noons' Landing and south to the Beach Point parking area.
- No long term road closures will be required during construction.
- Temporary road closures and lane reductions may be needed only during offloading of materials and equipment.
- Work is scheduled to be completed, and access restored to all affected aread, in mid-May 2019
Please be aware of signage in the area. Thank you for your patience and cooperation during this project.